Running smoothly – data center commissioning done right

Running smoothly – data center commissioning done right

9.4.2021 – Successful data center commissioning (Cx) ensures that the data center works like it is designed to – without downtime and with reasonable redundancy. To achieve this, no corners can be cut in the commissioning process.

Themes
Data and digitalisation
Share

In the world of data centers, technical systems such as constant cooling capacity and electrical power are directly critical to business. As essential it is to commission any facility correctly, commissioning takes on a whole new significance in data centers.

A small undetected equipment malfunction could lead to expensive downtime and damage the operator’s reputation. In turn, correct commissioning prevents revenue and credibility costing downtime as well as makes the data center provider’s job easier and more cost-effective in the years to come.

The commissioning team led by Cx Manager Juuso Saari is currently hard at work testing and making sure the most powerful supercomputer in Europe, LUMI (Large Unified Modern Infrastructure), has the optimal facilities to run. Operated by CSC, the supercomputer is situated in Kajaani, northeastern Finland, in a former paper mill turned data center.

“Commissioning is about quality assurance. We make sure every crucial technical system – be it ventilation, cooling systems, heat pumps, generators, electrical distribution systems, building automation – works the way it was designed and that all the systems work seamlessly together under any circumstances”, says Granlund’s Juuso Saari.

5 rules for a successful Cx

Early start

The commissioning process starts early in the design stage of the data center. “We make a very detailed commissioning plan and quality check it together with the data center provider. Mapping out the schedule and communicating to all parties what is expected of them before and during commissioning are also essential in the early stages of commissioning”, says Juuso Saari.

Holistic view

The commissioning team plays a huge role so selecting the Cx service provider is an important task. Besides vast technical knowledge and experience in data centers, the team needs to have a holistic view on the mechanisms and stakeholders of a data center.  Coordinating the process with the data center provider, contractors and system suppliers requires excellent communication and organizing skills.

Testing, testing

One of the key phases in commissioning is identifying and testing possible failure modes and scenarios. Through meticulous testing the potential problems are detected and solved early on. “When problems are found in the testing phase, they are a lot faster and cheaper to resolve than later on”, describes Otto Linna, the Cx team’s Mechanical Engineer and HVAC specialist. “Small problems can turn into big and costly problems if they are left undetected”.

Enough time

Good commissioning from planning, executing commissioning programs, conducting factory acceptance tests, testing on site, verifying results to documenting and reporting takes some time, but it is an investment that pays for itself. Furthermore, during the commissioning process, the data center operators get to know the systems and how they work. This makes it easier to run the data center in the future. Systematic documentation and reporting ensure that relevant data is accurate and accessible during and after the commissioning phase.

Constant communication

The commissioning calls for close co-operation among commissioning team, data center provider, contractors, and systems suppliers. Information needs to move quickly and accurately between stakeholders. ”Commissioning is also a great opportunity to share expertise and combine different points of view. We are constantly learning from each other”, mentions Otto Linna.

Get to know LUMI supercomputer

Located in the data center of CSC-IT Center for Science Ltd in Kajaani, the LUMI supercomputer has the computing power of 1.5 million state-of-the-art laptops. LUMI is owned by the European High-Performance Computing Joint Undertaking (EuroHPC JU). The organisation responsible for operating the supercomputer is the LUMI consortium. The consortium countries include Finland, Belgium, Czech Republic, Denmark, Estonia, Finland, Norway, Poland, Sweden, Iceland and Switzerland.

Want to hear more?

Jari Innanen

Business Director, Data centers
Granlund Oy

More of our news

Granlund designs specialised AI data centers for Nordic climate

29.10.2024 – The Artificial Intelligence boom creates a need for a new generation of data centers. An AI data center has unique…

NewsGROUP

Telia boosts data center capacity as artificial intelligence increases data center capacity needs

03.05.2024 – The proliferation of AI services increases the need for data centre capacity in the Nordic countries by around 30% per…

NewsGROUP

A good BIM model improves data centre usability

03.08.2023 – Building information modelling (BIM) helps in the scheduling of projects, among other things, and offers the opportunity for cost calculation…

NewsGROUP

Survey: The lack of high-quality data is an obstacle to digitalization in the construction and real estate sector

26.05.2023 – The digitalization of the real estate and construction sector requires investment and change has been slow, according to a survey…

NewsGROUP
Granlund Sweden people in a meeting

Granlund Sweden plays big role in data center business

11.04.2022 – A team of ten engineers is shaping the future of data center design. Now Granlund Sweden has plans to expand.

NewsSE
Lumi

LUMI Receives Honors in global DCD Awards 2021

09.12.2021 – LUMI has received honors in the global DCD Awards presented in London on 8 December 2021. LUMI was recognized with…

NewsGROUP

The key to a successful data center project

25.11.2021 – Granlund Sweden leads data center projects from conceptualisation to commissioning. Daniel Johansson and Jonas Olsson give five tips to successfull…

NewsGROUP

Running smoothly – data center commissioning done right

09.04.2021 – Successful data center commissioning (Cx) ensures that the data center works like it is designed to – without downtime and…

NewsGROUP

A supercomputer to heat houses in northern Finland

23.10.2020 – The efficient heat recovery system of the LUMI supercomputer will be optimised using a digital twin. In other data centres,…

NewsGROUP

Subscribe to our newsletter

Be amongst the first to hear about the latest news and trends relating to Granlund and the real estate and construction sectors.

Search